Three likely milestones, one unlikely plan
Give a recovery plan three milestones and rate them at 80, 70 and 60 per cent. Each looks better than a coin toss, yet the plan arrives whole only 33.6 per cent of the time, about once in three. Most valuations of troubled businesses are built on that one branch, the one where every milestone is met on schedule, and then trimmed by an adjustment that nobody can reconstruct afterwards.
Rajmarg Coachworks of Jalandhar builds bus bodies on chassis that its customers buy separately. Fatigue cracks appeared in a roof joint on bodies delivered to one large fleet operator. That customer stopped placing orders, rectifying the delivered bodies became a charge on cash, and several experienced welders left for competitors. Revenue has fallen from ₹240 crore to ₹150 crore, the business is losing ₹6 crore at the EBITDA level (operating profit before depreciation), and the plant is part-idle. Net debt, meaning borrowings less surplus cash, is ₹42 crore.
A note on the case: Rajmarg, its owners and its ledgers were put together for this article, and no real company's books sit behind them.
The owners' plan has three milestones. By month 6, the roof joint is redesigned, the design is certified by a testing house and the rectification claims are settled. By month 15, repeat orders return and the order book covers enough of the plant to stop the weekly loss. By month 30, margins settle where the plan says they will. The plan needs ₹17 crore of new money, which a special-situation lender (a lender that funds businesses in difficulty) has offered as a bridge, in three drawings, at an assumed 18% a year.
If everything goes right, Rajmarg again earns ₹22.8 crore of EBITDA on ₹240 crore of revenue, and a buyer at month 30 would pay about ₹116.9 crore for it. If the owners sold the land, plant and stock in an orderly sale today (one with time to find buyers), they would raise an assumed ₹35 crore. Every number that follows is assumed for illustration, and nothing here is a view on what any real turnaround is worth.
| Rajmarg at month 30 | Full recovery | Partial recovery |
|---|---|---|
| Revenue, ₹ crore | 240 | 215 |
| EBITDA margin | 9.5% | 7.5% |
| EBITDA, ₹ crore | 22.8 | 16.1 |
| Value then, ₹ crore | 116.9 | 63.0 |
| Value as a multiple of EBITDA | 5.1× | 3.9× |
| {: .amt } |
Each value is the first year's free cash flow after month 30 (cash left after tax, upkeep spending and working capital) divided by the discount rate less the growth rate: 13% less 4.5% for full recovery, 13% less 4.0% for partial. The 13% is the ordinary rate for a recovered body-builder. It carries no turnaround premium because the turnaround risk is going to sit elsewhere.
A scenario is an event with a date
The usual three-case set (upside, base, downside) fails first at the names. A "base case" hides the question that matters, which is whether it is the most likely outcome, the average outcome, or merely the one the sponsors prefer. The weights then become adjectives.
A scenario set that can be audited is built differently. Each branch is a sequence of observable events with a date: the testing house certifies the joint by month 6, or it does not. Each branch has its own cash needs and its own end value. The branches must not overlap, and together they must exhaust the possibilities, which forces the unpleasant ones onto the page. The most useful branch in a turnaround is the one in which the plan is abandoned, because it is what puts a floor under the value.
Rajmarg's set has four branches. The first gate (month 6) fails with probability 20%, and the owners sell. The second gate (month 15) fails with probability 30% after the first is passed, and they sell then. Having passed both, the business ends at full recovery with probability 60% or partial recovery with 40%. Multiplying along the branches gives 20.0%, 24.0%, 22.4% and 33.6%, which add to 100%.
These probabilities are judgements, not statistics. No dataset of coachbuilding turnarounds stands behind 80%, 70% or 60%, and this article quotes no industry success rate because none was read from a primary source. What gives the probabilities discipline is the way they are written down: each one is conditional on the gates before it, each is attached to an observable event, and each can later be scored against what happened. The next sections show how far they can be wrong before the decision changes.
Figure 1 · Assumed figures for one fictional plan
Rajmarg's recovery plan as a tree
View as a table
| Branch | Chance | Value today, ₹ crore |
|---|---|---|
| Gate 1 missed, sell at month 6 | 20.0% | 23.4 |
| Gate 1 passed, gate 2 missed, sell at month 15 | 24.0% | 12.8 |
| Both passed, partial recovery at month 30 | 22.4% | 28.6 |
| Both passed, full recovery at month 30 | 33.6% | 68.3 |
| Probability-weighted value | 100% | 37.1 |
What the tree says
Work backwards from the end. At month 30, the partial-recovery business is worth ₹63.0 crore against ₹24.1 crore owed to the bridge lender, which has been compounding at 18% on ₹8 crore drawn today, ₹6 crore at month 6 and ₹3 crore at month 15. That leaves ₹38.9 crore, or ₹28.6 crore in today's money at 13%. In the full-recovery branch the same arithmetic gives ₹68.3 crore.
When a gate fails, the owners decide whether to sell or carry on, and the tree records that decision. After a failed first gate, an orderly sale at month 6 raises about ₹33.6 crore (the ₹35 crore assumed for today, wearing away at 8% a year as people and orders leave), of which ₹8.7 crore goes to the bridge lender. After a failed second gate, a sale at month 15 raises about ₹31.5 crore, of which ₹16.6 crore goes to the bridge lender. In today's money, the four branches are worth ₹23.4 crore, ₹12.8 crore, ₹28.6 crore and ₹68.3 crore.
Weighted by their probabilities, they come to ₹37.1 crore. That is the value of Rajmarg to everyone who funded the business before the bridge, and it is 54% of the ₹68.3 crore that the plan shows when nothing goes wrong. Sale today is ₹35 crore. The plan is worth starting, but only by ₹2.1 crore, a margin smaller than the errors in the probabilities that produce it. The calculator below shows how quickly the margin disappears. The first gate has to be at least about 68% likely, against the 80% assumed. If the chance of passing it is 70%, the plan is worth ₹35.4 crore, barely above a sale.
Since net debt is ₹42 crore, equity looks negative on these figures: ₹37.1 crore less ₹42 crore is minus ₹4.9 crore. Owners do not lose more than their shares, though, and in every branch where the proceeds fall short of the debt the shortfall lands on the lenders. Taking the owners' payoff branch by branch and never below zero, only full recovery leaves anything for them (₹37.4 crore in today's money), so their expected equity is about ₹12.6 crore. Seen this way, the equity is closer to an option on the one branch that works than to the difference between two averages. It is an upper-side figure, because the model discounts it at the same 13% as the whole business, which is too low for equity that rests on one branch. The lenders' side of the same tree belongs to the article on valuation during financial distress.
Bridge money belongs inside the branches
The ₹17 crore of bridge money is drawn only if the owners continue, it is repaid before anyone else is paid from the exit, and its cost depends on how the story unfolds. At the assumed 18%, ₹17 crore drawn in three tranches costs ₹7.1 crore of interest by month 30. Raising the rate to 26% takes the plan's value to ₹35.3 crore and at 30% it stops being worth starting. Cheaper money helps less than one might expect: at 14% the plan is worth ₹38.0 crore.
The more important link is correlation. Operating results and financing do not move independently. A lender who sees a weaker recovery prices its next tranche higher, or declines it. If Rajmarg ends in partial recovery and the lender prices its second and third tranches 8 points above the 18% assumed, that branch loses about ₹1.1 crore in today's money and the expected value falls by ₹0.2 crore. The effect is small here because the branch is only 22.4% likely; it would be larger in a plan where a weak recovery is the likelier outcome. The scenario set should therefore state the funding terms branch by branch, rather than add a separate financing assumption on top.
Milestones share causes too. A deck usually states each milestone's chance as if it stood alone. The tree needs the chance of the second gate given that the first has been passed, and if both depend on the same people, such as the same plant head or the same customer, that conditional chance is higher than the stand-alone one. The table below shows how much rests on that single figure. The plan's headline value does not move at all as this figure changes, which is one reason the headline is a poor place to look.
| Chance of passing gate 2, once gate 1 is passed | 50% | 60% | 70% | 80% | 90% |
|---|---|---|---|---|---|
| Value of the staged plan, ₹ crore | 35.0 | 35.0 | 37.1 | 40.3 | 43.5 |
| {: .amt } |
At 50% and 60%, the plan is not worth starting and the value reverts to the ₹35.0 crore sale. A value that cannot fall below the exit is a feature of the tree and, as the next section shows, of the owners' right to stop.
The right to stop
Suppose instead that all three scheduled tranches become irrevocably committed at the outset and the owners cannot stop them, although the cash is still drawn at months 0, 6 and 15. The branches then change. A business that fails the first gate still receives and spends the later tranches, and ends at month 30 with whatever a sale would then fetch, ₹28.4 crore, less ₹24.1 crore owed to the bridge lender. The value of that unstoppable plan is ₹30.8 crore: lower than selling today.
The same plan with three stopping points is worth ₹37.1 crore. The difference of ₹6.4 crore (calculated before rounding the two values) is the worth of the right to stop. It comes from what the owners do not spend in the branches that fail and from what they keep of the sale value that has not yet eroded. Nothing about operations differs between the two plans. One requirement is that each gate is a real stopping point: a measurable fact, an agreed date, and cash released only after it is seen.
The same logic explains why waiting has a price. Waiting for more evidence before starting would delay every branch, and the assumed sale value is eroding at 8% a year, so the value of the sale option does not stand still. This article does not model a start delayed in that way.
Calculator
Run a gated plan through the tree
The defaults are Rajmarg's. Replace them with your own plan: two dated gates, the cash each releases, the bridge rate, the value of the recovered business and what a sale would raise. Amounts are in ₹ crore, in today's money. Timing is fixed: cash is drawn now, at month 6 and at month 15; gates fall at months 6 and 15; the end is month 30.
Result
- Plan with stopping points
- ₹37.1 crore
- Sell today
- ₹35.0 crore
- Same plan, no right to stop
- ₹30.8 crore
- Worth of the right to stop
- ₹6.4 crore
- Headline: every gate passed
- ₹68.3 crore
- Median branch
- ₹28.6 crore
- Gate 1 break-even chance
- 67.6%
- Owners' equity, branch by branch, never below zero
- ₹12.6 crore
| Branch | Chance | Value, ₹ crore |
|---|---|---|
| Gate 1 missed: sell at month 6 | 20.0% | 23.4 |
| Gate 2 missed: sell at month 15 | 24.0% | 12.8 |
| Partial recovery at month 30 | 22.4% | 28.6 |
| Full recovery at month 30 | 33.6% | 68.3 |
On these inputs the plan with stopping points is worth ₹37.1 crore against ₹35.0 crore from selling today, so it is worth starting by ₹2.1 crore. Without the right to stop it would be worth ₹30.8 crore. Gate 1 would have to be at least 67.6% likely for the plan to beat a sale, holding the other inputs. It is one set of judgements run through one tree, not a valuation of any company.
Averages, middles and prices
The tree produces four numbers that people tend to call "the value".
The most likely single branch is full recovery, at 33.6%, worth ₹68.3 crore. It is the number in the owners' deck. The median is the branch that sits in the middle once the branches are ranked by value, which is partial recovery at ₹28.6 crore; half the probability lies below it and half above it. The mean is ₹37.1 crore. And the sale is ₹35.0 crore.
Figure 2 · Assumed figures for one fictional plan
Four branches, one mean, and a sale price in the middle
View as a table
| Branch or reference | Chance | Value today, ₹ crore |
|---|---|---|
| Sell at month 15 | 24.0% | 12.8 |
| Sell at month 6 | 20.0% | 23.4 |
| Partial recovery (median branch) | 22.4% | 28.6 |
| Full recovery (most likely branch) | 33.6% | 68.3 |
| Mean of the four branches | 37.1 | |
| Sale today | 35.0 |
No branch pays any of those figures except the first, and the first has a 66.4% chance of not happening. The mean is a planning figure: it is the number to compare with other uses of the same money. The median tells a risk-averse owner what a typical outcome looks like and, in this case, it is below the sale value. A buyer's price cannot be read from the tree. It depends on the buyer's own plan, funding and tolerance for being wrong, and a buyer who cannot see the gates will tend to offer something near the sale value. A buyer who can be shown the gates can be offered a price paid in stages. The owners can then ask for the ₹35 crore floor and share the rest only if the gates are met.
The standards allow all of this. The International Valuation Standards (IVS, effective 31 January 2025) say in IVS 200 (paragraph 60.13) that many businesses are valued on a single scenario but that multi-scenario models may be used where there is significant uncertainty about the amount or timing of cash flows. IVS 103, Appendix paragraph A20.16, lists the types of cash flow a forecast can represent, and A20.17 notes that a limited number of discrete scenarios and probabilities can stand in for a full distribution.
One rate cannot do what a tree does
Many valuers allow for turnaround risk by adding a few points to the discount rate. IVS 103, in paragraph A20.37(c) of its Appendix, accepts that higher dispersion among possible outcomes may call for an adjustment to the rate. For a business like Rajmarg a single uplift still hides what drives the value. The rate cannot pay out in lumps, because value jumps when a gate is passed. It cannot stop at the sale value, because a rate applied to the plan's cash flows has no floor. And it cannot represent a bridge lender whose payoff comes before the owners'. After the first gate is passed, the expected value moves from ₹37.1 crore to ₹40.6 crore; after the second, to ₹52.5 crore. A fixed uplift has no mechanism to make that move, since it does not know which gates exist.
Risk placed in the rate and the same risk placed in the cash flows should not both be charged; the article on why DCF values are so sensitive to assumptions covers it, and this article keeps the 13% ordinary for that reason.
Figure 3 · Assumed figures for one fictional plan
What each gate does to the value
View as a table
| Position | Value today, ₹ crore |
|---|---|
| Today, before any gate | 37.1 |
| After gate 1 passed | 40.6 |
| After gates 1 and 2 passed | 52.5 |
| Gate 1 missed, business sold | 23.4 |
| Gate 2 missed, business sold | 12.8 |
| Sale today (reference) | 35.0 |
What decision-useful reporting looks like
A single figure for Rajmarg would be easy to produce and hard to use. A report that helps the owners, and anyone reading it later, shows the following. The expected value (₹37.1 crore) next to the sale value (₹35.0 crore). The range by branch (₹12.8 crore to ₹68.3 crore), with the probability of each. The gates, with dates and what is released at each. The break-even probability for each gate (67.6%, 63.3% and 50.4% on the assumptions here), which says how wrong the sponsors can be before the answer changes. And the assumptions that move the result most. IVS 106, paragraph 30.06, requires a valuation report to state significant assumptions and the rationale for the value reported.
Several things are left out of the model, and they are not trivial. Interest on the existing ₹42 crore of debt is treated as part of the stage cash needs; lenders' consent, covenants and any change in their terms are not modelled. Nor are losses carried forward for tax, the owners' own incentives to continue, customers lost while the plan runs, partial asset sales, refinancing risk for the bridge at month 30, or any difference between the owners' view of the probabilities and a lender's. Cash flows between gates are collapsed to the dates shown, and the probabilities are judgements that no data set confirms.
To test a plan of your own, write each milestone as a dated, observable fact. Beside it put the cash that has to be committed to reach it and what you will actually do if it is missed. Then value the business twice at each gate, once if you stop and once if you carry on, using the calculator above if useful. A milestone for which both values are close does not change any decision, and its probability does not belong in the valuation. A milestone for which they are far apart is the one whose evidence deserves the money, the date and the independent check.
Talking it through
If a valuation question is in front of you, a conversation about purpose, scope and the information needed is usually the right first step.
Technical notes
- All amounts are in ₹ crore, in today's money unless a month is named. The business, the 80%, 70% and 60% chances, the 18% bridge rate, the 13% discount rate, the ₹35 crore sale value and its 8% yearly erosion, the ₹42 crore of net debt and the ₹8, ₹6 and ₹3 crore drawings are assumed for illustration. None is an observed market figure, a typical success rate or a typical cost of rescue finance. The article cites no turnaround success rate because none was read from a primary source.
- Scale check for the invented business: recovered revenue ₹240 crore and about 700 people (₹34 lakh of revenue per person, a body-builder that buys chassis separately); EBITDA margin 9.5% (partial recovery 7.5%); depreciation ₹6.0 crore; net debt ₹42 crore, 1.8 times recovered EBITDA; full-recovery value ₹116.9 crore, 5.1 times EBITDA; partial recovery ₹63.0 crore, 3.9 times. Today's revenue ₹150 crore and EBITDA loss of ₹6 crore are context only and enter no calculation.
- Method: values at month 30 are next year's free cash flow divided by (13% less growth): ₹9.94 crore ÷ 8.5% and ₹5.67 crore ÷ 9.0%, rounded to ₹116.9 crore and ₹63.0 crore and used as rounded. The tree is solved backwards from month 30: at each gate the owners take the larger of selling and continuing. Cash is drawn at months 0, 6 and 15; the bridge compounds at 18% a year from each drawing and is repaid first from the exit. A sale at a missed gate raises ₹35 crore × 0.92 to the power of elapsed years, less the bridge owed. Discounting is at 13% with fractional years.
- Rounding: the staged value is ₹37.12 crore and the unstoppable plan ₹30.76 crore. The shown 37.1 and 30.8 differ by 6.3, but the difference before rounding is 6.4, which is the figure used for the value of the right to stop. The full-recovery branch is ₹68.3 crore after discounting (₹116.9 crore less ₹24.1 crore owed, divided by 1.13 to the power of 2.5); subtracting the rounded figures by hand gives the same to one decimal. Branch chances 20.0%, 24.0%, 22.4% and 33.6% add to 100%.
- Not modelled: interest on the existing ₹42 crore beyond what is inside the stage cash needs, lenders' consent and covenants, tax on losses carried forward, owners' incentives to continue or stop, customers and staff lost while the plan runs, partial asset sales, refinancing of the bridge at month 30, any start delayed to wait for evidence, and any difference between the owners' and a lender's view of the probabilities. The equity line discounts the owners' payoff at the same 13% as the whole business, which understates the return that levered equity would require, so it is an upper-side illustration. This is an educational model, not a valuation report.
References
Checked on 6 November 2026. Cited in general terms only.
- International Valuation Standards Council, International Valuation Standards (effective 31 January 2025): IVS 200 Businesses and Business Interests, paragraph 60.13 (single-scenario and multi-scenario or simulation models where there is significant uncertainty about amount or timing of cash flows); IVS 103 Valuation Approaches, Appendix paragraphs A20.16 and A20.17 (types of projected cash flow; limited discrete scenarios and probabilities) and A20.37(c) (dispersion of outcomes and the discount rate); IVS 106 Documentation and Reporting, paragraph 30.06(n) and (p) (significant assumptions; value and rationale). Read from a published copy of the standards; the IVSC site was not used for the text. www.ivsc.org
About this article
This article and its illustrations are for general education. They are not a valuation, a valuation report under any law, or advice on any transaction, tax or regulatory matter.
A valuation for a real decision depends on the facts, the purpose, the date, the applicable law and standards, and the information available. Please seek professional advice before relying on any figure.
Rajmarg Coachworks, its welders, its fleet customer and each rupee figure belong to this page alone; no company's books were opened to write them.